How long does a tub-to-shower conversion take?
Two numbers answer that, and treating them as one is where the confusion comes from. On site, a tub-to-shower conversion takes 1–2 days — the same as a straight tub or shower replacement — and a full bathroom remodel takes 3–5 days. That is how long the bathroom is out of use. The wait to start is separate: about 4–6 weeks from the day you approve your proposal for a conversion, and about 8–10 weeks for a full remodel, because everything is ordered to your selections rather than pulled off a shelf.
Last updated August 2026 · Every proposal carries a projected schedule with real dates on it, and the price it is built from comes from our Estimate Builder.
The two numbers, side by side
| Project | Days on site | Wait to start |
|---|---|---|
| Tub-to-shower conversion | 1–2 days | 4–6 weeks |
| Tub or shower replacement | 1–2 days | 4–6 weeks |
| Full bathroom remodel | 3–5 days | 8–10 weeks |
Days on site is how long the bathroom is unusable. Wait to start is counted from the day you approve the proposal, not from the day you first call.
You get the schedule in writing before anything is torn out. The itemized proposal you approve carries a projected schedule: when we start, how many days we are in the house, and what happens on each. A span of days on a website is an average of other people's bathrooms. The dates in your proposal are yours.
What happens on each of the two days
Day one — demolition, haul-away, plumbing and the pan
Protection goes in before anything comes out. Then the tub, the old surround and the old valve trim come out, and they leave in our truck rather than sitting on your curb. With the wall open, a scald-safe Delta valve goes in where the old one was and the drain is set — a conversion keeps both where they already are whenever the bathroom allows it, which is the single biggest reason this is measured in days rather than weeks. Then the pan goes in, set level and fully bedded so it never flexes or creaks underfoot, and the waterproofing goes on around it. Day one usually ends with a finished floor and open walls.
Day two — walls, door, trim and the cleanup
The wall system goes up against a pan that is already set: groutless panels cut to your alcove, seams sealed, corners closed. Then the shower head and the valve trim, then the door or the curtain rod. Anything you added as a priced option goes on at the same time — grab bars, a fold-down seat, a hand sprayer on a magnetic dock, a diverter. Those four are options you choose and pay for rather than fittings that arrive by default; the Delta valve and the shower head are the two in every package. Through September 30, 2026, a deposit placed by that date includes all four — the grab bars, the seat, the sprayer and the diverter — on any package at no extra cost. Then the room is cleaned and the protection comes up on the way out.
What lands a job on one day instead of two
- Which wall system you picked. The acrylic kit is the shortest install — one kit, every piece cut to meet the next, sliding glass door already inside it. A groutless stone, solid-surface or composite wall is a panel-by-panel glue-up with seams that need time to set, and it is the one most likely to want the second day.
- Whether the drain and the valve stay put. They usually do. Moving either is real plumbing work with the floor open, and it belongs in the written proposal rather than in a surprise on demolition day — which is what the photos you send us are for.
- What is behind the tub. Straight studs and a sound subfloor are quick. Anything else is the next section.
- How much you added. A recessed niche, a glass door on a package that ships with a curtain, bars and a seat each take their own time. Not much alone. Enough together to be the difference.
What actually moves a date
Three things account for nearly every schedule that slips, and none of them is a crew working slowly.
- Custom glass is measured after the walls are set, never before. A door made to fit your opening cannot be ordered off a drawing, because the opening does not exist yet. On the three packages where a glass door is an upgrade rather than part of the kit, the walls go in, the opening is measured, and the glass follows on a short return visit — the shower is finished and usable behind the curtain and rod in the meantime. It is the most common reason a finish date moves, and the least alarming one.
- A special-order colorway. Thirteen colorways in one system, eighteen in another, twelve in another. Most are pulled from stock; a few are made to order, and those add their lead time to the wait to start rather than to the days on site. Ask which side of that line a color sits on before you settle on it.
- A structural surprise. Floor joists, damaged studs, anything holding the house up — the things nobody can see until the wall is open. If we find one, we stop, show you photographs and a price, and you approve it in writing before we do the work; the same goes for a waste stack that has to move or anything needing licensed abatement, and nothing else moves a guaranteed price. Rot is not on that list. All the wall backing comes out and all the plumbing behind the shower is replaced as part of the job, so soft drywall and failed backing in there are material we were replacing anyway, and if the subfloor directly under the tub or shower we remove is damaged, we replace it, however much of it there is, at no additional charge and without a change order — a term of the agreement you sign, so it adds a few hours to the day and nothing to the price. One September offer does have a date: place your deposit by September 30, 2026, and the grab bar pair, the fold-down shower seat, the Moen Magnetix hand sprayer and the 3-setting diverter valve — normally priced options — are included on any package at no extra cost.
Why there is a wait to start at all
Nothing about your shower is stocked. Once you approve a proposal, the wall system in the colorway you chose, a pan in the size your room actually takes, the valve, the trim and the door are ordered against that selection, and the deposit at signing is what reserves the install date and places the order. About 4–6 weeks is the honest span for it. That is not a queue you are standing in — it is the time your materials take to be built and shipped.
How a full remodel differs
A full bathroom remodel is 3–5 days on site and roughly 8–10 weeks from approval, because it is a different job. The room comes out to the studs and the subfloor, the layout can change while the walls are open, rough plumbing and electrical happen before anything closes up, and then the shower, the tile, the vanity, the fixtures and finally the custom glass. Ordering is what stretches the front end: tile, cabinetry, fixtures and glass each carry their own lead time, and the work cannot start until the slowest has landed. The full remodel page and the conversion page cover what each includes, and the Columbus cost guide covers what moves the number.
What your own decisions do to the clock
- Send photos that show the whole bathroom. They find the drain relocation or the odd framing before we price it rather than after, and they are the condition your guaranteed price rests on.
- Settle selections before we order. A choice made two weeks late does not cost two weeks. It costs two weeks plus the lead time behind the thing you chose, which is usually the larger half.
- Decide the glass configuration early, even though the glass is measured late. That is what stops the measurement being the first time anybody has thought about the door.
- Add options while the order is still open. A grab bar added before the order goes in is a line on it. The same bar afterward is a second order with its own shipping.
About the bathroom done in one day
Several national brands advertise a bathroom finished in a single day, and it is a real product doing a real thing: a one-piece acrylic system set over the existing footprint, with the walls and the base made to drop into the space the tub leaves behind. It is quick because the variables are kept down on purpose — same footprint, one material, one way of fitting it. For somebody who wants the tub gone, does not want to choose anything and needs the bathroom back tonight, that is a sensible buy.
What the second day buys is range. Ours is 1–2 days because it covers six wall systems rather than one — Acrylic, Bestbath, Palisade glue-up tile, Trinity stone-look, Transolid solid-surface and Castico solid composite stone — and because the pan is set, bedded and waterproofed rather than dropped in. Four of the six sit on a one-piece pan you can walk or roll straight into with no step at all; acrylic has a low step-in. A groutless wall wants seam time, and a made-to-fit glass door wants the walls to exist before it is measured. We do not advertise one day, because across most of our jobs it would be a best case dressed up as a promise. Where a job genuinely is one day — an acrylic kit in a straightforward alcove with the plumbing staying put — your schedule says one day, because it is your schedule and not a slogan.
Dust, and the rest of your house during those days
The bathroom being worked in is out of use for the whole 1–2 days. Nothing else needs to be. Taped rigid floor protection runs the path from your door rather than a drop cloth that slides and lets grit underneath, a plastic barrier wall closes the doorway, HEPA air scrubbers run through demolition, and the registers are covered so nothing ends up in your ductwork. The site is left tidy at the end of each day, and the room gets at least two full professional cleanings before we hand it back rather than one at the end. None of it is an upgrade line on your proposal.
The blue-tape walkthrough
At the end we walk the finished bathroom together, in daylight, with an hour set aside and a roll of blue tape. You mark anything you want us to look at, and every taped item goes onto one written punch list with an outcome recorded beside it. You get a copy before we leave.
When the crew is there, and when we are
Crews are on site Monday through Friday. The office is reachable Mon–Fri 9:00–4:30 to talk to a person, and Saturday is by appointment only. The website itself never closes: the Design Studio, the Estimate Builder and the quote form all work at any hour of any day.
The guarantee, and where we work
Every bathroom we build carries a lifetime leak-free guarantee: if the pan or the walls we install ever leak, we fix it, for as long as the original buyer owns the home. Workmanship carries five years, and so do finish and adjustment items — caulk, grout shrinkage, paint touch-up, hardware adjustment. The products carry their own makers' coverage. Read what the guarantee covers, in plain English. We are based in Westerville and work across Columbus and the suburbs around it, in Franklin, Delaware, Licking and Fairfield counties.
Common questions
How long does a tub-to-shower conversion take?
On site, 1–2 days, which is how long your bathroom is out of use. The wait to start is a separate number: about 4–6 weeks from the day you approve your proposal, because the wall system, the pan, the valve and the door are ordered to your selections rather than pulled off a shelf. Your itemized proposal carries a projected schedule before anything is torn out.
How long does a full bathroom remodel take?
Three to five days on site, and about 8–10 weeks from approval before those days arrive. A gut carries far more ordering than a conversion does — tile, vanity, cabinetry, fixtures and custom glass, each with its own lead time — and the work cannot start until the slowest of them has landed.
Why is there a wait before the work starts?
Because nothing is stocked to fit your bathroom. Once you approve the proposal, your wall system in the colorway you chose, a pan in the size your room takes, the valve, the trim and the door are all ordered to that selection, and the deposit at signing is what reserves the install date and places the order. About 4–6 weeks is the honest span for that on a conversion. If a colorway you want is a special order rather than a stock item, ask before you settle on it and we will tell you which side of that line it falls on.
Can a tub-to-shower conversion be done in one day?
Some of ours are. An acrylic kit in a straightforward alcove, with the drain and the valve staying where they already are, can go in and be finished inside a single day. We publish 1–2 days rather than one because a groutless stone or solid-surface wall and a properly waterproofed pan often want the second day, and we would rather quote the honest span than the best case. A single-day system is a real product: a one-piece acrylic surround set over the existing footprint, quick because the choice set is deliberately narrow. Ours covers six wall systems instead of one.
What usually causes a bathroom project to run late?
Three things account for nearly all of it. Custom glass is measured against the walls after they are set rather than off a drawing, so a made-to-fit door follows the install rather than arriving with it. A colorway that has to be made rather than pulled carries its own lead time. And a structural surprise behind the wall — floor joists, damaged studs, anything holding the house up — stops the work until you have seen what it costs and approved it in writing.
Can I use my bathroom while you are working, and how much dust is there?
The bathroom being worked in is out of use for the 1–2 days the crew is there, which is why the days-on-site number matters more than the calendar. The rest of your house stays usable: taped rigid floor protection goes down the whole path from your door rather than a drop cloth, a plastic barrier wall closes off the bathroom doorway, HEPA air scrubbers run through demolition, and the registers get covered so nothing ends up in your ductwork. The room gets at least two full professional cleanings before we hand it back, not one at the end.
Do I get a schedule in writing before you start?
Yes. The itemized proposal you approve carries a projected schedule — when we start, how many days we are there and what happens on each of them — before anything is torn out. Crews work Monday through Friday, so if the calendar would put a weekend in the middle of your job, that shows on the schedule you approved rather than turning up as a surprise on a Saturday morning.